Insurance insights

We provided initial reports to ABP for insurance companies after this berth was damaged, and oversaw the repairs.

A 1,000 tonne mobile crane weighing 70 tonnes, with 150 tonnes of counterweight attached to the crane and a further 180 tonnes supported on the 'super lift' platform, was used to lift the linkspan back into place.

A parallel set of maintenance works including replacing the pontoon hulls was also able to be done while the facility was out of service, minimising 'down time'.